Monday, July 6, 2015

Renos - Day 43 - 47

Its been a slowish week in reno land. In fact all was quiet in the house between Wednesday and Friday but to be fair we were warned that this would happen as the next stage begins. Various tradies will arrive to do their bit.

The beginning of the week saw the plasters continue patching up the walls and ceilings.



Waterproofing of the wet areas began ready for the tiler....
the ensuite


the bathroom


The toilet finally found its way outside!!


The new sliding door was fitted.




and the cladding is now finished well except for the painting